A twelve years story of waste of social resources: The Mexico-Toluca Interurban Train
Main Article Content
Abstract
The general objective of this paper is to make an ex-post evaluation of the Mexico-Toluca Interurban Train project (TIMT) more than nine years after the beginning of its construction stage. The present study is based on the cost-benefit analysis approach, through which some analysis scenarios have been built and whose results are contrasted with the official project evaluations. The present research has focused on the analysis of the TIMT as a microcosm of the scarce efficiency of public investment in Mexico, resulting in a waste of social resources. According to the results of the study, the combination of delays and cost overruns (186% in nominal terms, 114% in real terms, and 90% in dollars) has configured a project (across two Federal Government Administrations) with negative social profitability, with losses valued at more than 550 million dollars, placing it in the most problematic quartile of train projects in the world.
Downloads
Article Details
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
References
Andric, J.M., Mahamadu, A.M., Wang, J., Zou, P.X.W. & Zhong, R. (2019). The cost performance and causes of overruns in infrastructure development projects in Asia. Journal of Civil Engineering and Management, 25(3), 203-214. https://doi.org/10.3846/jcem.2019.8646
Annema, J.A., Frenken, K., Koopmans, C. & Kroesen, M. (2017). Relating cost-benefit analysis results with transport project decisions in the Netherlands. Letters in Spatial and Resource Science, 10, 109-127. https://doi.org/10.1007/s12076-016-0175-5
Auditoría Superior de la Federación (2021a). Suministro y Puesta en Marcha de Material Rodante, Sistemas Ferroviarios y de Comunicaciones, Boletaje, Centro de Control, Sistemas Electromecánicos del Túnel y del Viaducto, Vías, Sistemas de Energía y Construcción de Dos Subestaciones de Tracción de 25 Kv y Edificios Técnicos en Línea del Tren Interurbano México-Toluca, en el Estado de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 356-DE: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2021b). Trabajos de Construcción y Obras Complementarias del Tramo 3 del Tren Interurbano México-Toluca, en la Ciudad de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 329-DE: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2022a). Construcción de la Estación Vasco de Quiroga del Tren Interurbano México-Toluca, en la Ciudad de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 294: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2022b). Construcción del Tramo Ferroviario Zinancatepec km 0 + 000 al km 36 +150 del Tren Interurbano México-Toluca, en el Estado de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 295: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2022c). Construcción del Túnel Ferroviario del Portal Poniente al Oriente, con inicio en el km 36 + 150 y Terminación en el km 40 + 478, y Adequaciones, Actualizaciones y Modificaciones al Proyecto Ejecutivo del Tren Interurbano México-Toluca, en el Estado de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 296: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2023a). Trabajos de Construcción y Obras Complementarias del Tramo 3 del Tren Interurbano México-Toluca, en la Ciudad de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 308: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2023b). Construcción de la Estación Vasco de Quiroga del Tren Interurbano México-Toluca, en la Ciudad de México. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 303: http://www.asfdatos.gob.mx/
Auditoría Superior de la Federación (2023c). Avances del Proyecto de Construcción del Tren Interurbano México-Toluca. México: Auditoría Superior de la Federación, Sistema Público de Consulta de Auditorías, Número de Auditoría 288: http://www.asfdatos.gob.mx/
Bnamericas (2021, 18 de agosto). Los principales problemas del tren de US$4,600mn Ciudad de México-Toluca. https://www.bnamericas.com/es/reportajes/los-principales-problemas-del-tren-de-us4600mn-ciudad-de-mexico-toluca
Bocanegra, R. (2020, 30 de octubre). Licitarán dos nuevas obras del Tren Interurbano México-Toluca. Real Estate Market & Lifestyle. https://realestatemarket.com.mx/noticias/ infraestructura-y-construccion/30750-licitaran-dos-nuevas-obras-del-tren-interurbano-mexico-toluca
Bhargrava, A., Anastasopoulos, P., Labi, S., Sinha, K. C. & Mannering, F. L. (2010). Three-stage least squares analysis of time and cost-overruns in construction contracts. ASCE Journal of Construction, Engineering and Management, 136(11), 1207–1218. DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000225
Burnside, C., & Dollar, D. (2004). Aid, policies, and growth: Revisiting the evidence. World Bank Policy Research Working Paper, No. 2834. https://documents.worldbank.org/en/publication/ documents-reports/documentdetail/992381468780325835/pdf
Canitez, F., Celebi, D. & Beyazit, E. (2019). Establishing a metropolitan transport authority in Istanbul: A new institutional economics framework for institutional change in urban transport. Case Studies on Transport Policy, 7(3), 562–573. https://doi.org/10.1016/j.cstp.2019.06.002
Cantarelli, C., Flyvbjerg, B. & Buhl, S.L. (2012). Geographical variation in project cost performance: the Netherlands versus worldwide. Journal of Transport Geography, 24(C), 324-331. 10.1016/j.jtrangeo.2012.03.014
Carapia, F. (2021, 12 de septiembre). Está Línea 3 lejos de meta planeada. Mural. https://www.mural.com.mx/esta-linea-3-lejos-de-meta-planeada/ar2257188
Chavarín, R. (2023). When government wastes benefits from a project: The case of Line 3 of Light Rail in Guadalajara, Mexico. Paradigma Económico, 15(2), 39-64. http://dx.doi.org/10.2139/ssrn.4241368
Clinnick, R. (2022, March 24). Stuttgart 21 project cost increases by €950m. International Railway Journal. https://www.railjournal.com/infrastructure/stuttgart-21-project-cost-increases-by-e950m/
CUESTIONE (2021, 10 de octubre). A pesar de multas y sobrecosto en obra, SCT otorga contrato a ICA para Tren Interurbano. https://cuestione.com/nacional/a-pesar-de-multas-y-sobrecosto-en-obra-sct-otorga-contrato-a-ica-para-tren-interurbano/
Dollar, D., & Levin, V. (2005). Sowing and reaping: Institutional quality and project outcomes in developing countries. World Bank Policy Research Working Paper, No. 3524. https://elibrary.worldbank.org/doi/abs/10.1596/1813-9450-3524
Eliasson, J., & Lundberg, M. (2012). Do cost–benefit analyses influence transport investment decisions? Experiences from the Swedish Transport Investment Plan 2010–21. Transport Reviews 32(1), 29-48. 10.1080/01441647.2011.582541
Flyvbjerg, B. (2007a). Policy and planning for large-infrastructure projects: problems, causes, cures. Environment and Planning B: Planning and Design, 34(4), 578-97. https://ssrn.com/abstract=2230414
Flyvbjerg, B. (2007b). Cost overruns and demand shortfalls in urban rail and other infrastructure. Transportation Planning and Technology, 30(1), 9-30. https://doi.org/10.1080/03081060701207938
Flyvbjerg, B. (2009). Survival of the unfittest: Why the worst infrastructure gets built – and what we can do about it. Oxford Review of Economic Policy, 25(3), 344–367. https://doi.org/10.1093/oxrep/grp024
Flyvbjerg, B., Skamris-Holm, M.K. & Buhl, S.L. (2003a). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71-88. 10.1080/0144164022000016667
Flyvbjerg, B., Bruzelius, N. & Rothengatter, W. (2003b). Megaprojects and Risk: An Anatomy of Ambition. Cambridge University Press, 8th edition.
Flyvbjerg, B., Skamris-Holm, M.K. & Buhl, S.L. (2004). What causes cost overrun in transport infrastructure projects? Transport Reviews, 24(1), 3-18. https://doi.org/10.1080/0144164032000080494a
Han, S.H., Yun, S. Kim, H., Kwak, Y.H., Park, H. K. & Lee, S. H. (2009). Analyzing schedule delay of mega project: lessons learned from Korea train express. IEEE Transactions on Engineering Management, 56(2): 243-256. 10.1109/TEM.2009.2016042
Huo, T., Ren, H. Cai, W., Shen, G. K., Liu, B., Zhu, M. & Wu, H. (2018). Measurement and dependence analysis of cost overruns in megatransport infrastructure projects: Case study in Hong Kong. Journal of Construction Engineering and Management, 144(3). 10.1061/(ASCE)CO.1943-7862.0001444
Ika, L.A., Diallo, A. & Thuillier, D. (2012). Critical success factors for World Bank projects: An empirical investigation. International Journal of Project Management, 30(1), 105–116. https://doi.org/10.1016/j.ijproman.2011.03.005
IMCO (2018). Ineficiencia y riesgos de corrupción en obra pública: caso de estudio del tren interurbano México-Toluca. https://imco.org.mx/ineficiencia-riesgos-corrupcion-obra-publica-caso-estudio-del-tren-interurbano-mexico-toluca/
Kostka, G., & Anzinger, N. (2016). Large infrastructure projects in Germany: A cross-sectoral analysis. En G. Kostka & J. Fiedler (eds.) Large Infrastructure Projects in Germany. (pp. 15-38) Palgrave Macmillan.
Lagarda, G., Linares, J., López, A. & Manzano, O. (2018). Management and execution of investment projects, the task prior to the measurement of development effectiveness: The case of the Inter-American Development Bank. IDB Working Paper Series, IDB-WP-918. https://publications.iadb.org/en/management-and-execution-investment-projects-task-prior-measurement-development-effectiveness-case
Lee, J. K. (2008). Cost overrun and cause in Korean social overhead capital projects: Roads, rails, airports, and ports. Journal of Urban Planning and Development, 134(2), 59-62. 10.1061/ASCE0733-94882008134:259
Legovini, A. (2010). Development impact evaluation initiative: A World Bank-wide strategic approach to enhance developmental effectiveness. World Bank Report, No.63322. https://documents.worldbank.org/en/publication/documents-reports/documentdetail/ 689141468161083406/development-impact-evaluation-initiative-a-world-bank-wide-strategic-approach-to-enhance-developmental-effectiveness
Meunier, D. & Welde, M. (2017). Ex-post evaluations in Norway and France. Transportation Research Procedia, 26, 144-155. https://doi.org/10.1016/j.trpro.2017.07.015
Obras Expansión (2018, 15 de junio). El tren México-Toluca comenzará a rodar hasta mediados de 2019. https://obras.expansion.mx/construccion/2018/06/15/el-tren-mexico-toluca-comenzara-a-rodar-hasta-mediados-de-2019
SENERMEX (2013). Análisis Costo Beneficio. Proyecto: construir el tren interurbano México-Toluca 1era etapa. México: SENERMEX Ingeniería y Sistemas.
SENERMEX (2018). Análisis Costo Beneficio. Tren interurbano México - Toluca. México: SENERMEX Ingeniería y Sistemas.
SENERMEX (2020). Memoria del Análisis Costo - Beneficio (ACB) del proyecto del Tren Interurbano México-Toluca. México: SENERMEX Ingeniería y Sistemas.
SHCP (sin fecha). Calendario de Financiamiento del proyecto: Tren Interurbano México-Toluca https://www.secciones.hacienda.gob.mx/work/models/sci/cartera_publica/ , clave de cartera: 13093110008.
Singh, R. (2010). Delays and cost overruns in infrastructure projects: extent, causes and remedies. Economic and Political Weekly, 45(21), 43-54. https://www.jstor.org/stable/27807050
Steininger, B., Groth, M. & Weber, B. L. (2020). Cost overruns and delays in infrastructure projects: the case of Stuttgart 21. KTH Royal Institute of Technology Working Paper, No. 2020/11. S-WoPEc. https://swopec.hhs.se/kthrec/abs/kthrec2020_011.htm
Williamson, O.E. (2000). The New institutional economics: Taking stock, looking ahead. Journal of Economic Literature, 38(3), 595–613. https://www.jstor.org/stable/2565421
Winston, C., & Maheshri, V. (2007). On the social desirability of urban rail transit systems. Journal of Urban Economics, 62(2), 362-82. 10.1016/j.jue.2006.07.002
Zavala, D. (2023, 08 de agosto). Tren Interurbano México-Toluca: 10 años de construcción y desafíos de ingeniería. Obras Expansión. https://obras.expansion.mx/infraestructura/2023/08/08/tren-interurbano-mexico-toluca-avances-inauguracion